Teams using Siteaware capture
For teams performing Siteaware capture, 2 scans should be performed per pour area:
- When the deck is approximately 70-80% complete (typically at the end of the workday 2 days before the pour).
- When the deck is 95-100% complete (typically at the end of the workday before the pour).
Teams performing self-capture
Teams performing self-capture can scan as many times as they want before the pour. For example, teams can scan at the completion of each trade's work to verify their installation and then again after any potential deviations are corrected.
To achieve the full benefit of the Siteaware system, it is recommended to scan at least 2 times before the pour.