When entering the Pour Verification Area, you will, by default, be taken to the pour readiness page of the most recent scan.
The pour readiness page helps to provide a quick overview of how ready your project teams are for a pour.
The Scan Summary Panel
On the left-hand side of the page is a pour summary showing the overall readiness of the pour including the projected pour time. As the pour approaches a countdown will appear to highlight for all team members that their time to finish their installation is running out.
Trade Cards
Each trade is broken down to show how many open elements remain so that you can focus on the most critical issues in the limited time you have before the pour.
On this pour:
- The plumbing trade is 89% Ready.
- The plumbing trade has closed out 5 elements for the GC's review.
- There are 3 open observations that have not yet been addressed.
- There are 26 elements that have not yet been installed.
- Siteaware was unable to verify 4 of the planned elements for this pour and they should be field-verified to ensure they are properly installed prior to the pour.
Clicking on the Open Issues button will take the user to the Map View with that trade filtered.
Navigating Between Pours
You can navigate between pours by clicking on the Level-Pour dropdown at the top of the page.